Technical Specification for Information System Integration: What to Check Before the Tender Is Published

In these tenders, the work is to connect two or three systems: an accounting system, a CRM, a payment gateway, a government agency service. The customer is usually a government body or a large company whose systems already work separately, while data between them is still moved by hand or through files. API integration is supposed to remove that manual work. A well-written technical specification for information system integration is what makes that outcome achievable.

What makes integration special is that the contractor does not fully control any of the sides. One system belongs to the customer, another to a vendor or an agency, a third to a bank or a gateway operator. Anything about the connection between them that the specification does not fix is later settled by negotiation rather than engineering.

That is why the outcome of the project is largely decided at the specification stage. In a typical document the systems are named and the goal is stated, but the description of the exchange itself is reduced to a line or two. Below are the places where such specifications most often fall short, and what should be written there.

What specs usually miss

The systems are named, but there is no description of their API and no statement of who will provide it

What it leads to. The contractor sets the price and timeline blind, based on assumptions about methods, formats and the authentication approach. After the contract is signed, it turns out that no documentation exists and the owner of the second system is under no obligation to provide it. Work stalls, the deadline slips, and the contract names no one as responsible.

How to write it right. Add a section called "Source data for integration": for each system, the version, the interface type, and a link to the current documentation or an appendix to the specification. State on a separate line who hands over access to the documentation and by when after the contract is signed, and what counts as a delay caused by the customer.

Behavior during an exchange failure is not described

What it leads to. A payment went through but is not reflected in the accounting records. A request was sent but no response came back. If the specification does not say what the system does in such cases, the contractor chooses on their own, and at acceptance the customer discovers that duplicates, lost records or silent failures are not acceptable to them. There is nothing to argue from: the requirement did not exist.

How to write it right. Describe failure scenarios explicitly: the other side being unavailable, a timeout, an error response, the same message being sent again. For each one, state what the system does: retries the request, puts it in a queue, flags the record, notifies someone responsible, and exactly whom. Separately, require protection against duplicates on retries.

The other side has no test environment, and this is not addressed anywhere

What it leads to. The integration has to be tested on the live system or not tested at all. In the first case, real data and payments are at risk; in the second, errors surface after launch. Acceptance testing formally passes against stubs, and real exchange happens for the first time on launch day.

How to write it right. In the specification, state which systems need a test environment, who provides it, and by when. If a party has no test environment, write down the alternative: an emulator, an agreed set of test data, or a testing window on the live system with its limitations described. Tie acceptance testing to that environment.

Responsibility for data at the junction between systems is not allocated

What it leads to. When the amount or status in one system differs from the other, each side considers the other's data to be wrong. The contractor says they passed on what they received. The owner of the source system says it is working normally. The customer is left without an answer as to who corrects the data and who is accountable for it.

How to write it right. Include a section on data ownership: for each exchanged object, which system is the source of truth, who is responsible for the quality of the source data, and who is responsible for transformation during transfer. Define the procedure for handling discrepancies: who records them, who fixes them, and within what time.

There is no requirement for an exchange log

What it leads to. A dispute about whether a message was sent, what it contained and what response came back cannot be resolved without records. Without a log, incident analysis turns into comparing participants' recollections, and claims against the contractor or the owner of the neighboring system remain unproven.

How to write it right. Require an exchange log as a separate clause: what is recorded (time, direction, operation identifier, status, error code), how long it is kept, who has access to view it, and how personal and payment data in the records are protected. State that the log serves as the basis for resolving disputes.

Acceptance is described in general terms: "the integration works"

What it leads to. Without verifiable criteria, the acceptance certificate can be left unsigned indefinitely or signed without anything substantial having been checked. Both sides end up in a position where any assessment of the result is subjective.

How to write it right. For each exchange scenario, draw up a list of checks: input data, expected result, testing environment. Include in acceptance the negative scenarios from the failure section and a check of the log. Formulate the condition for signing the certificate as passing these checks.

What a good spec gives

The customer gets a tender in which contractors price the same scope of work, so their bids can be compared with one another.

The boundaries of responsibility between systems and parties are set in advance, so disputed situations are resolved by the document rather than by ad hoc agreement.

The contractor sees the source data and the testing conditions before filing the bid and can estimate the timeline and cost honestly.

Acceptance follows checks known in advance, and the launched integration stays in operation instead of becoming a source of manual corrections.

Price and timeline

Technical specification: from $400, 1-4 weeks; the price depends on the system's complexity, architecture, stack and integrations. Subcontracted development: priced by contract scope, estimated before the bid is filed.

Tender specs or subcontracting: details →

We do not name buyers or tenders: we look at a typical spec, not at anyone's procurement.